Learn how RB group leveraged 3D documentation to save more than $150k on labor costs
“So we went down, captured the area, compared it, and one of the walls was quite far out. So we were able to flag it immediately, and it was immediately obvious, but when you walked around with the tape measure and a laser measure and checked it, it all seemed fine.If you didn’t catch it, you’re looking at many, many weeks and many hundreds of thousands of pounds, in terms of cost and delay.”
Seán McKirdy
Director of RB Plant Construction